National Energy entrusted us with the construction of a 5.5MW solar park, with a budget of €2,000,000.00.

Services Provided

  • Execution of all necessary studies, including Energy Performance Study, Electromechanical Studies, and Geotechnical Study for soil assessment and selection of installation method
  • Installation of fencing in accordance with required specifications
  • Land grading and preparation
  • Construction of access roads
  • Drilling of foundation holes for the installation of the tracker foundation piles (movable support base for photovoltaic panels)
  • Installation of 1,700 foundation piles using concrete piling
  • Assembly of 151 trackers
  • Installation of photovoltaic panels
  • Installation of inverters
  • Laying of Low Voltage (LV)
  • Laying of Medium Voltage (MV) cables
  • Installation of DC cables
  • Installation of CCTV system
  • Installation of SCADA monitoring system
  • Installation of a Substation, including all necessary civil and electrical works

Client Benefits

  • Project completion within the initial budget
  • Digitized supervision with client access
  • In-house Project Manager - accurate timeline
  • Detailed reporting system to the client
  • Advanced Technology & Automation

Other Data

Number of specialized technicians > 80